TonysRV10.com
Home | Contact Me | Helpful Links | N584TA | About Me
 Tony's RV-10 Build   Dec-5-2024   


  Sect 41 - Instrument Panel

  Sect 25-26 - Fuselage
  Sect 9 - Elevators
  Sect 8 - Horizontal Stabilizer
  Sect 7 - Rudder Assembly
  Sect 6 - Vert. Stabilizer
  Building Work Tables

  Workshop












 
RV-10 :: Section 6 - Vertical Stabilizer

Jan 31, 2020 - Test fit skin to check for the bump
Feb 2, 2020 - Skin clecoed, ready to match drill. No bump!
Feb 16, 2020 - Everything primed and ready.. frame is riveted!!
Feb 26, 2020 - Vertical Stab is complete.


 

 
Status / Completed

08/01/21 - QB Wings Ordered
05/15/21 - New QB Fuse Delivered
04/25/21 - QB Fuse Returned
04/09/21 - Instrument Panel Delivered
12/2/20 - QB Fuse Delivered
11/29/20 - Hor. Stab Complete
05/2/20 - Rudder Completed
03/20/20 - Ordered QB Fuse
02/26/20 - V. Stab Completed
02/07/20 - Reserved N584TA
01/24/20 - Start Vertical Stabilizer
01/16/20 - Building Work Tables
01/02/20 - Ordered Empennage Kit
12/27/19 - Ordered Tools Cleaveland Tools Kit
8/2/19 - Preliminary Schedule Complete
7/5/19 - Working through preliminay schedule
7/1/19 - Planning, researching, etc.


   TonysRV10.com
Home | Contact Me | Helpful Links | N584TA | About Me
 Tony's RV-10 Build   Dec-5-2024   
Van's Aircraft
Van's Home Page
RV-10 Page
RV-10 Specs
Van's Air Force
Facebook Pages
RV-10 Group
Vans Aircraft Builders
Zenith Aircraft
Airplane Kit Building
EAA
Kitplanes Magazine
Homebuilt Homepage
Other Great Airplane Kits
Zenith Aircraft Company
Kitfox Aircraft
Sonex Aircraft
The Airplane Factory



Copyright 2019-2024 tonysrv10.com all rights reserved