TonysRV10.com
Home | Contact Me | Helpful Links | N584TA | About Me
 Tony's RV-10 Build   Apr-24-2024   


  Sect 41 - Instrument Panel

  Sect 25-26 - Fuselage
  Sect 9 - Elevators
  Sect 8 - Horizontal Stabilizer
  Sect 7 - Rudder Assembly
  Sect 6 - Vert. Stabilizer
  Building Work Tables

  Workshop












Schedule

 
2022
   July
Section 9 - Elevators
 
   August
Section 9 - Elevators
 
   September
Section 9 - Elevators
 
   October
Section 9 - Elevators
 
   November
Section 10 - Tailcone
 
   August
Section 10 - Tailcone
 
   September
10 - Tailcone
 
   October
10 - Tailcone/
 
   November
Finalize Tail Sections Order Antenna
 
   December
Plan wiring, conduits
 
 
2023
   January
Electronics Installation Plan
 
   February
Antenna Plan / Install /
 
   March
Start wiring electrical
 
   March
Order Engine and Prop
 
   April
Review QB Fuse Completion, Tailcone misc installation
 
   May
Attach Tailcone to fuse,A/C Install, AP Install tail and wingsn
 
   June
Rudder Pedals/Control System,
 
   July
Instrument Panel
 
   August
Cabin Wire, switches, misc wires, Wing Wire, lights
 
   September
QB Wings Delivery, Cabin Top / Doors
 
   October
Cabin Top / Doors, Wing Wiring
 
   November
Firewall prep, Flap Install
 
   December
Engine Mount, Wing Wiring
 
 
2024
   January
Spinner and Cowling
 
   February
Fairings / Wheelpants
 
   March
Seats, trim, restraints, Cabin Heat / AC
 
   April
Move to Hanger / Assemble
 
   May
Final checks
 
   June
Flight Tests
 
   July
 
   August
 
   September
 
   October
 
   November
 
   December
 


 

 
Status / Completed

08/01/21 - QB Wings Ordered
05/15/21 - New QB Fuse Delivered
04/25/21 - QB Fuse Returned
04/09/21 - Instrument Panel Delivered
12/2/20 - QB Fuse Delivered
11/29/20 - Hor. Stab Complete
05/2/20 - Rudder Completed
03/20/20 - Ordered QB Fuse
02/26/20 - V. Stab Completed
02/07/20 - Reserved N584TA
01/24/20 - Start Vertical Stabilizer
01/16/20 - Building Work Tables
01/02/20 - Ordered Empennage Kit
12/27/19 - Ordered Tools Cleaveland Tools Kit
8/2/19 - Preliminary Schedule Complete
7/5/19 - Working through preliminay schedule
7/1/19 - Planning, researching, etc.


   TonysRV10.com
Home | Contact Me | Helpful Links | N584TA | About Me
 Tony's RV-10 Build   Apr-24-2024   
Van's Aircraft
Van's Home Page
RV-10 Page
RV-10 Specs
Van's Air Force
Facebook Pages
RV-10 Group
Vans Aircraft Builders
Zenith Aircraft
Airplane Kit Building
EAA
Kitplanes Magazine
Homebuilt Homepage
Other Great Airplane Kits
Zenith Aircraft Company
Kitfox Aircraft
Sonex Aircraft
The Airplane Factory



Copyright 2019-2024 tonysrv10.com all rights reserved